Vacuum Equipment Acceptance Criteria

FAT and acceptance records for vacuum equipment.

Vacuum equipment FAT Acceptance records

Acceptance criteria

CriterionTypical evidence
Vacuum performanceultimate pressure, pump-down curve, pressure-rise curve, leak-test report
Process controlrecipe execution, data log, alarm history, MFC and power-supply readbacks
Thermal performancetemperature stability, ramp behaviour, TUS record if required
Mechanical integrationfixtures, feedthroughs, seals, doors, manipulators and access points
Safetyinterlocks, overtemperature, cooling flow, gas safety and emergency stop
Documentationmanuals, electrical diagrams, pneumatic diagrams, calibration records, spare-parts list

FAT structure

  1. visual inspection and configuration check
  2. cold vacuum test and pressure-rise test
  3. gas-flow and MFC check
  4. thermal or plasma-source functional test
  5. process demo with exported data log
  6. alarm, interlock and safety check
  7. documentation handover